Please see the links below for this month’s footage of Paul Harding / EAU progress update:
https://weigandconstruction.egnyte.com/dl/GWftbvy7qJQ8
YouTube Link: https://youtu.be/RogsB-N_z0c
Below is a brief high-level update of construction activities that have been taking place onsite, as well as the activities to be expected within the coming month.
Past Progress:
CM Mobilization and Temp. Fence Install
Earthwork Equipment Mobilization
Cut Main Entry Hill to Grade and Form, Prep, Pour Temporary Entry Sidewalk.
Forthcoming Progress:
Site Demolition – Sidewalks & Curbs Within Fenced Areas
Cut Grade and Bring in Stone for Laydown Areas Within Fencing
Start Site Utilities Installation, Rework, and Demo.