Construction at PHJH

Here is the high-level update of construction activities that have been taking place at Paul Harding Jr. and East Allen University, as well as the activities to be expected within the coming month.

Past Progress:

CM Mobilization and Temp. Fence Install

Earthwork Equipment Mobilization

Cut Main Entry Hill to Grade and Form, Prep, Pour Temporary Entry Sidewalk.

Forthcoming Progress:

Site Demolition – Sidewalks & Curbs Within Fenced Areas

Cut Grade and Bring in Stone for Laydown Areas Within Fencing

Start Site Utilities Installation, Rework, and Demo.